The Central Utah Water Conservancy District (CUWCD), together with Ames Construction, are installing the Salem Reach 1 segment of the Spanish Fork/Santaquin Pipeline--a 60 inch steel pipe to be buried within the Salem Canal Road from Elk Ridge Drive to Woodland Hills Drive. The existing Salem Canal (open canal and shallow pipe) will be removed, lowered and replaced with a 42-inch HDPE pipeline.
In addition, Salem City is using this opportunity to install new storm drains along portions of Salem Canal Road, 300 West, 100 East, 500 East, and 300 South, as well as additional curb and a public trail along the north side of Salem Canal Road (see map below). Also, Salem Canal Road will be straightened by shifting the roadway southward between 500 East and 240 East and installing a full-width city street. After all the work is complete, a new asphalt surface will be placed along Salem Canal Road.
PROJECT AREA MAP
SALEM CANAL ROAD
UPDATES
The project is nearing completion; the Salem Canal has been removed and replaced with underground pipe, installation of the 60-inch pipe is complete, and storm drains have been installed in various locations. However, construction crews continue some work to finish utility work, fencing, landscaping, and road reconstruction.
LANDSCAPING
Crews are now onsite and have begun work for irrigation/sprinkler and landscaping restoration.
SAFETY
PLEASE, BE CAREFUL! For your own safety and others, pay close attention to workers, signs and equipment, and maintain a safe distance when driving, biking or walking near construction work zones.
NO ENTRY ZONES
Signs and barriers are positioned for your safety. Do not move existing barricades, signs, or enter taped-off areas; violators may be fined.
START DATE
MAY 2022
EST. COMPLETION DATE
MAY 2024
WORK DAYS
MON - FRI
WORK HOURS
7:00 AM - 6:00 PM
PHOTOS
CONTACT
Contact Us
HOTLINE: 877-458-2463
EMAIL: SalemReach1@gmail.com
Please contact the public information team with any questions or concerns.
STAY INFORMED
We encourage you to sign up for the weekly email updates so that you are aware of potential impacts. Send an email to salemreach1@gmail.com and enter "Salem Reach Updates" in the subject line.